Billing With Payment Requests and Retainage (G702/G703-Style)

Submit AIA-style payment requests, hold back retainage, and close out on the Expert plan.

J
Written by Joseph Kibe

On bigger jobs, you don’t just send an invoice. You submit a request for payment, and you show your work: what’s done, what’s stored on site, what’s been held back. Payment requests in Eano give you that process. Each request draws down your payment milestones, holds back retainage automatically, produces an Application for Payment and a Continuation Sheet modeled on the AIA G702 and G703, and turns into an invoice once it’s approved.

Payment requests and retainage are only available on the Expert plan. If you’re on Starter or Pro, see Getting the Expert Plan below.

Why It Matters

Commercial owners, lenders, and architects expect a standard paper trail. When every request lists the scheduled value, previous billings, this period’s work, stored materials, retainage, and balance to finish line by line, everyone can check your numbers the same way. Eano does the math as you type and keeps a running record across every request, so your fifth request picks up exactly where your fourth left off.

Think of your milestones as the schedule of values, and each payment request as one page in the pay app binder.

Getting the Expert Plan

On Starter or Pro, payment requests don’t show up anywhere in the app. You won’t see the New Payment Request button, the Requests for Payment section on the Finances tab, or the retainage fields in Edit Milestones. Nothing’s broken. They’re switched on by the Expert plan.

To upgrade:

  1. Click the card icon in the top bar, just left of the Settings gear. It’s labeled Plans & Billing when you hover over it.

  2. Find the Expert card, choose monthly or annual billing, and click Upgrade.

  3. Once you’ve upgraded, refresh the page. Payment requests and retainage are ready to use on every project.

If you don’t see the card icon, your role doesn’t manage billing. Ask your account Owner to upgrade. Not sure Expert is right for your business? Chat with us and we’ll walk through it with you.

Before You Start: Set Retainage on Your Milestones

Retainage is the portion of each payment that’s held back until the end of the job. It’s part of your contract terms, so you set it before the client signs.

  1. Open the opportunity and go to the Payment Milestones tab.

  2. Click Edit Milestones.

  3. On each payable milestone, set:

    • General Retainage: held back from completed work.

    • Material Retainage: held back from materials stored on site.

  4. Use the % / $ picker next to each field to choose a percentage or a fixed dollar amount.

  5. Click Save.

Setting General Retainage and Material Retainage in Edit Milestones

Each milestone can have its own retainage, and a milestone template keeps whatever retainage you saved on it. Once any milestone has retainage, your proposal and contract show General Retainage and Material Retainage columns, so your client sees the terms before signing.

Creating a Payment Request

Payment requests live on the project’s Finances tab, under Income. They’re available as soon as the contract is signed.

The New Payment Request and Create Close Out buttons on the Finances tab

  1. Go to the project’s Finances tab and make sure Income is selected.

  2. Click New Payment Request. (You’ll also find + New Payment Request under Requests for Payment, below the income list.)

  3. Check the Period To date and change it to the end of your billing period if needed. The Application Date is today.

  4. For each milestone you’re billing this period, fill in:

    • Amount to Request: the dollar value of work completed this period.

    • Total Materials Stored: the total value of materials currently stored on site for that milestone. This is a running balance, not just what arrived this period.

  5. Watch the %, Balance to Finish, and Retainage columns update as you type.

  6. Click Create Request.

A new payment request with amounts entered for three milestones

Leave a row blank to skip that milestone this period. A milestone that’s already fully billed shows a green check and its fields are locked.

When stored materials get installed

This is the one part that trips people up. Say you billed $8,000 of tile as stored materials last period, and this period the tile is installed. On this request:

  • Set Total Materials Stored to what’s still sitting on site ($0 if all of it went in).

  • Include the installed $8,000 in Amount to Request, along with any new work.

If you lower the stored balance without adding the installed value to Amount to Request, that value drops out of your completed total and the milestone looks less finished than it really is. When material retainage is higher than general retainage, moving materials into completed work frees up the difference, and Eano works that out for you.

Reviewing, Approving, and Invoicing

Every request appears under Requests for Payment with its Request ID, Date, Amount Requested (before retainage), Current Payment Due (after retainage), Status, and linked Invoice.

The Requests for Payment list

Click the request ID or either amount to open the details. You’ll see the Application for Payment (the G702-style summary, lines 1 through 9), the Change Order Summary, and the Continuation Sheet (the G703-style line-by-line breakdown) as one document.

Payment request details showing the Application for Payment summary

The Continuation Sheet in payment request details

A request moves through these statuses:

  • Open: created, not approved yet.

  • Approved: you’ve signed off on it and can invoice it.

  • Invoiced: the invoice is created.

  • Partial Payment: the client has paid part of the invoice.

  • Paid: the invoice is paid in full.

  • Voided: the request was voided and no longer counts toward the project.

To invoice a request:

  1. Open the request and click Mark as Approved (or switch the status from Open to Approved in the list).

  2. Click + Create Invoice.

  3. Pick the payment terms or due date, then click Save, or Save & Send to Client to send it right away.

The invoice has one line per milestone, already net of retainage, and its total matches Current Payment Due. The lines can’t be edited, so the invoice always matches the request. Your client pays it like any other Eano invoice.

Downloading the RFP and Continuation Sheet

Each row in Requests for Payment has two downloads:

  • RFP: the Application and Certificate for Payment, a PDF modeled on the AIA G702. It includes the contractor’s certification, a notary block, and a blank architect’s certificate for projects where an architect signs off.

  • Continuation: the Continuation Sheet, a PDF modeled on the AIA G703.

Your client doesn’t get these documents from Eano. If the owner, lender, or architect needs them, download them and send them along yourself. They follow the AIA layout but aren’t official AIA forms.

Closing Out and Releasing Retainage

Once every milestone has been fully requested, New Payment Request turns into Create Close Out.

  1. Click Create Close Out.

  2. Review the Retainage to Release for each milestone, and the Total Retainage to Release at the bottom.

  3. Click Create Close Out.

The Create Close Out dialog listing retainage to release by milestone

The close out is a special payment request for the retainage you’ve held back. It goes through the same steps as any other request: approve it, invoice it, get paid. If no retainage was held on the project, there’s nothing to release and you won’t see a close out.

You can create a close out even while earlier requests are still Open or Approved. Eano asks you to confirm first, because once a close out exists, earlier requests can no longer be voided.

Fixing Mistakes: Voiding

A request is final the moment you create it. It can’t be edited or deleted, so the paper trail stays intact. If something’s wrong, void it and create a new one.

  • Void the request: open the request (or use the ⋯ menu) and click Void Request. This works while the request is Open, Approved, or Invoiced. If it’s Invoiced, the linked invoice is voided too, and you can choose to notify the client. The request’s amounts come off the project’s payment progress.

  • Void just the invoice: if only the invoice needs fixing, void the invoice from the invoice itself. The request goes back to Approved so you can create a new invoice. The voided invoice stays on the request, crossed out, for your records.

A paid request can’t be voided. If you need to give money back, use a credit change order instead.

A Few Things Worth Knowing

  • Once you use payment requests, the project bills through them. After the first request, you can’t mark milestones as paid directly or link a manual invoice to a milestone, even if you later void every request. Marking a milestone complete just records that the work is done. It no longer sends your client a payment request. You can still create regular invoices for anything that isn’t a milestone.

  • Clear out older milestone billing first. If the project has any unpaid milestone payment requests or milestone invoices, Eano lists them when you open your first payment request. Collect or void them before continuing. Anything billed before your first request counts as previously completed, with no retainage held on it.

  • Retainage is locked after signing. Once the contract is signed, you can’t change a milestone’s retainage. Projects you create directly from Projects count as signed from the start, so they can’t have retainage. You can still use payment requests on them without it.

  • Fixed-dollar retainage is spread across the milestone. If you hold back $1,000 on a $10,000 milestone, each request withholds the same share (10%), so you’ve held exactly $1,000 by the time the milestone is fully billed.

  • The fixed amount can’t be more than the milestone. If a scope change shrinks a milestone below its fixed retainage, Finalize Quote shows Fix milestone retainage until you lower the retainage or adjust the milestone.

  • Material retainage lower than general retainage gets a warning. Eano lets you save it, but when stored materials are installed, more retainage is withheld at that point.

  • Need to bill more than a milestone’s value? A request can’t take a milestone past 100%. Add a change order first.

  • Setting retainage turns off the automatic first payment request. If any milestone has retainage, Send first payment request after signing won’t fire, because billing runs through your payment requests instead.

  • Very large requests need splitting. A single request can’t have a Current Payment Due over $999,999.99. Split the work across two requests.

  • Who can use payment requests. Owners and Admins can use them on every project, and Core Members only on projects they’re assigned to. Subcontractors and Field Workers can’t see payment requests at all.

  • If you change plans, projects that already have payment requests keep working, but you can’t start them on new projects or set retainage without the Expert plan.

FAQ

I can’t find New Payment Request. Where is it? It’s on the project’s Finances tab, with Income selected. If it isn’t there, your team isn’t on the Expert plan, or your role doesn’t have access. Subcontractors and Field Workers never see it, and Core Members only see it on projects they’re assigned to. To upgrade, see Getting the Expert Plan above.

Is this the official AIA G702 and G703? No. The RFP and Continuation follow the same layout and line numbers so they’re familiar to owners and architects, but they’re Eano documents, not AIA forms.

Does the architect approve the request inside Eano? Not yet. You mark requests approved yourself. If your project has an architect, download the RFP and Continuation, send them over, and mark the request Approved once you hear back. The RFP includes a blank architect’s certificate they can sign.

Can I enter a percentage instead of a dollar amount on a request? Amount to Request is entered in dollars. The % column shows how complete each milestone will be after the request, so you can check your work as you type.

Why is Create Request greyed out? Usually one of three things: every row is blank or zero, a row has an error (like going over the scheduled value), or the project still has older milestone billing to collect or void first.

Why can’t I void an earlier request? Either it’s already paid, or you’ve created a close out. Void the close out first if you need to change an earlier request.

I added a change order after closing out. Now what? Approved change orders that came after the close out can be billed and paid directly, without retainage.

Can my client see the payment request? Your client gets the invoice, and pays it the usual way. To give them the RFP or Continuation, download the PDFs and send them yourself.