Open a project or opportunity's Schedule tab on the web and click Export to download a printable PDF. Choose Calendar for a one-page day, week, or month, or Gantt for a task list and timeline that can span several pages.

A printout is handy for the crew's morning meeting, a job-site noticeboard, or someone who prefers a paper copy. Choose the view and dates before exporting so the PDF covers the work you want to share.

Export a Project Calendar

  1. Open the project or opportunity and select its Schedule tab.

  2. Choose Calendar.

  3. Open the View dropdown and choose Day, Week, or Month. Use the arrows or Date picker to reach the period you want.

  4. Use All Events to choose which event types to include.

  5. Click the blue Export button above the calendar. It reads Exporting… while the PDF is prepared, then the file downloads to your computer.

The project's Schedule tab in Calendar view, with Export above the calendar.

The PDF uses the selected view: Day prints that day, Week prints that week, and Month prints the month grid. Each Calendar export fits on a single landscape page.

Open the View dropdown to choose Month, Week, or Day before exporting.

For example, choose Week to hand the crew a plan for the coming week, or Month for a broader overview. You don't have to leave the project or filter the company-wide schedule down to one job.

Export a Project Gantt Schedule

  1. Open the project or opportunity's Schedule tab and choose Gantt.

  2. Set the zoom and scroll the timeline horizontally to the dates you want on paper. Use Zoom to fit if you want to bring the scheduled work into view first.

  3. Adjust All Events if you want to narrow the event types included.

  4. Click Export in the Gantt toolbar.

The project Gantt toolbar includes Zoom to fit, the zoom selector, and Export. The task list also shows an unscheduled task with no due date.

The Gantt PDF includes the full filtered list, including tasks without dates and rows below the part of the list you can see on screen. Long lists continue onto additional pages, so you don't need to scroll down and export each section separately.

The printed timeline uses the zoom and horizontal date range you're viewing, rounded outward to whole days. If your view begins or ends partway through a day, the export includes that whole day. Tasks outside the printed date range still appear in the list, but their bars only appear where they overlap that range. Unscheduled tasks appear without a dated bar.

Export the Company Calendar

To print a schedule across projects, choose Schedule in the left sidebar and click Export in the Calendar controls.

The company-wide Calendar export produces a full month, even when you're viewing Week or Day. For a day or week from a single job, use that project's own Schedule tab instead.

Your company-calendar filters carry into the PDF, including Only show my tasks, Tags, Status, Assignee, and Events. Its project/status color setting carries over too. You can use these to prepare a focused printout for one assignee or a milestones-only overview.

A Few Things Worth Knowing

  • Calendar and Gantt handle page space differently. Calendar stays on one page and can summarize crowded days with a +N count. Gantt continues the task list over more pages as needed.

  • Calendar follows the weekend display setting. If your team has Hide tasks on weekends enabled under Display Settings, the Calendar PDF uses that display setting too. See Keeping Weekends and Holidays Off Your Schedule.

  • Exporting doesn't change the schedule. It downloads a copy. If dates or tasks change later, export again for an up-to-date printout.

  • Let the view finish loading. Export can be unavailable while Calendar or Gantt is updating. In Gantt, an empty list also leaves Export unavailable.

Frequently Asked Questions

Can I export just one project's schedule?

Yes. Open that project's Schedule tab, choose Calendar or Gantt, and click Export.

Can I print a week or a single day?

Yes, from a project's Calendar. Choose Week or Day in View before exporting. The company-wide Calendar export still produces a full month.

Will Gantt export tasks I haven't scheduled yet?

Yes. Unscheduled tasks are included in the filtered list, with no dates or timeline bar. The export also includes rows below the visible part of the task list.

How do I print more of the timeline?

Adjust the Gantt zoom or use Zoom to fit before exporting. Scrolling vertically doesn't limit the exported list; the horizontal timeline view determines the printed date range.

Why does my Calendar PDF show a +3 instead of every event?

Calendar exports fit on one page, so crowded days can summarize extra events. Narrow the event types, or use a project's Day or Week view for a more focused printout.